​A permit extension is unlikely to be accepted if a previous extension for that permit has already been granted. ​

​Yes, if you no longer will be proceeding with construction, you can request to revoke your permit. The same application form is used for this process. 

Download the Revocation Request Form​

In some cases, depending on how far construction is progressing, we may deny your request for revocation. Submit the application form to permit.expediter@brampton.ca. There is no fee to revoke a permit.​

​If you intend to complete construction, yes, you need to request an extension to your permit. 

Download the Permit Extension Application ​

Email the completed application to permit.expediter@brampton.ca​. If approved, an extension fee of $243.84 will be applicable and the permit will be valid for a maximum of six months after the original date of expiry.

You would have received a building permit card when your permit was issued. The second page of the building permit card indicates the mandatory inspections required for your permit (Sample​).

​Before you extend the permit, you will need to you to transfer the ownership of the original permit into the new owner’s name. Please complete a Transfer of Ownership Request Form and submit it to building.inquiries@brampton.ca​.  You will receive payment link to process the fee for the transfer of ownership. 

​If your permit is about to expire and work has already started, you need to begin booking inspections.

Book an Inspection Online​​