Start of Construction - Purpose of this site meeting is to identify any questions the contractor has, if any, especially regarding notes from plans examiners (if not already done so during permit pick up) prior to construction. Also reviewing required reports/certificates and fences to prevent hazardous condition to public.
Footing - At ready stage for pouring concrete, excavation complete, forms in place (or trench excavated) on undisturbed soil free of standing water, mud and loose earth
Backfill - Ready for backfilling of foundation, dampproofing applied, weeping tile covered with stone (min. 6 inches of cover)
Structural Framing - Prior to insulation but after rough ins are complete and passed (plumbing, hvac and electrical)
Fire Separations, Closures and Fire Stopping - Fire separations fully complete as per design details and/or listed systems
Interior Finishes - Interior finishes completed including but not limited to trim, paint and doors, normally done with occupancy and/or final inspection
Fire Alarm Systems - Fire alarm systems complete and verified and all paperwork ready to be submitted to the inspector, systems also ready to be tested in presence of the inspector
Sprinkler and Standpipe Systems - Sprinkler and/or standpipe systems complete, tested and paperwork ready to be submitted to the inspector, systems also ready to be tested in presence of the inspector
Emergency Lighting and Power - Emergency lighting and power systems complete, tested and paperwork ready to be submitted to the inspector, systems also ready to be tested in presence of the inspector
Fire Access Routes - Fire access route complete with reports confirming capable of supporting fire department’s equipment
Occupancy - Notice of completion must be submitted (NofC form) prior to occupying the newly constructed space or part of, once all applicable inspectors pass occupancy inspections an occupancy permit (sample) will be issued and mailed to owner within 5 business days
PUBLIC POOLS - Pool Deck, Dressing Rooms and Emergency stop systems complete and Pool form completed and ready for submission to inspector
Final - All construction is complete, interior and exterior including grading. Once passed by all applicable inspectors a Certificate of Final Inspection will be sent within 10 business days