Footing - At ready stage for pouring concrete, excavation complete, forms in place on undisturbed soil free of standing water, mud and loose earth
Engineered Fill - P. Eng. Report - Final subgrade and wall reinforcement (if required) reports must be submitted to building inspector prior to framing inspection
Perimeter insulation (Slab-on-grade) - Slab-on-grade insulation inspection in walk-out and some look-out conditions
Backfill - Ready for backfilling of foundation, damp proofing applied, weeping tile covered with stone (min. 6 inches of cover)
Weeping Tile Connection - If pre-sewered, inspected at backfill
Structural Framing - Prior to insulation but after rough ins are complete and passed (plumbing, hvac and electrical)
Fire Separations - Upon completion, usually coincides with framing inspection, usually occurs in semis and townhouses
Basement Finish Structural Framing - Prior to insulation but after rough ins are complete and passed (plumbing, hvac and electrical)
Occupancy - Once all applicable inspectors pass occupancy inspections an occupancy permit (sample) will be issued and mailed to owner within 5 business days
Final - All construction is complete, interior and exterior. Once passed by all applicable inspectors a Certificate of Final Inspection will be sent within 10 business days